a. Upon receipt of equipment, unpack the contents and perform the following checks:

(1) Inspect the equipment for damage incurred during shipment. If the equipment has been damaged, report the damage on SF 364, Report of Discrepancy (Packaging).

(2) Check the equipment against the packing slip to see if the shipment is complete. Report all discrepancies in accordance with the instruction of AR 735-11-2.

b. RECOIL MECHANISM. Verify that the recoil damper rod position and fluid level are correct. Place recoil housing cap over damper rod and install headed straight pin. The indicator rod must protrude a minimum of 0.5 in. (12.7 mm) past the end of the damper housing assembly, but not more than 1.1 in. (27.2 mm). If the measurement is incorrect, service damper reservoir in accordance with WP 0049 00.